Utility-scale solar park in an arid landscape
Segments

Ground-mounted solar parks

Utility-scale solar power plants, built turnkey from the first soil test to the connection to the transmission grid.

A power plant, not just a field of modules

A solar park only delivers its forecast yield if every part fits together: foundations, structures, cables, stations, substation and grid connection. We plan all of it together and deliver it at a fixed price.

Over the past 20 years we have delivered numerous utility-scale plants in Europe and South America together with large engineering firms. We bring this experience, and the lessons learned from very different climates and grids, to projects across Africa.

Aerial view of a solar park in South Africa

Our scope of delivery

Everything a utility-scale plant needs, from one general contractor.

  • Site selection and land assessment
  • Soil investigation and pull-out tests
  • Yield forecast and CO₂ calculation
  • Fixed-tilt structures or single-axis trackers
  • DC and AC cabling
  • Inverter and transformer stations
  • Medium-voltage collection grid
  • Substation and high-voltage connection
  • Monitoring and plant control (SCADA)
  • Battery energy storage (BESS) as an option
  • Grid studies and grid code compliance
  • Fencing, security and access roads
  • Commissioning and grid compliance tests
  • Handover, O&M documentation and training of local staff

How the power reaches the grid

The modules generate direct current, central inverters convert it to alternating current, the transformer station raises the voltage and the plant feeds into the grid via a substation. A battery can store energy for the evening peak.

PV modulesDCCentral invertersDC → ACTransformer stationLow → medium / high voltagePublic gridSubstation and transmission lineSolar power (DC)AC low voltageMedium / high voltageBattery storage (optional)Charge / discharge

Challenges we solve on African sites

Building a solar park in Africa is different from building one in Europe. These are the issues that decide whether a project stays on time and on budget, and how we deal with them.

Heat and high module temperatures

Challenge

High ambient temperatures reduce module output and stress inverters and cables.

Our approach

Modules with a low temperature coefficient, ventilated inverter stations and cable cross-sections sized for local ambient temperatures.

Dust and soiling

Challenge

Sand and dust on the modules can cost several percent of the annual yield.

Our approach

Tilt angle, row spacing and access routes planned for cleaning, plus a water-saving cleaning concept included in the yield forecast.

Soil and geotechnics

Challenge

Rock, loose sand or clay determine which foundation will hold.

Our approach

Soil investigation and pull-out tests before planning, then the right choice between rammed posts, pre-drilling, ground screws or concrete foundations.

Weak grids and grid codes

Challenge

Many grids have limited capacity and strict requirements for reactive power and fault behaviour.

Our approach

Grid studies at an early stage, close coordination with the utility, and inverters and substations designed to the local grid code.

Logistics and customs

Challenge

Long transport routes, port handling and import procedures can delay a project by months.

Our approach

Procurement plan with lead times, experienced forwarders and material staging close to the site.

Security and theft

Challenge

Remote sites are exposed to theft of cables and components.

Our approach

Fencing, lighting and video surveillance, buried cable routes and theft-resistant fastening of modules.

Heavy rain and drainage

Challenge

Short, intense rainfall can wash out foundations and cable trenches.

Our approach

Drainage planning based on terrain and rainfall data, erosion protection and raised equipment foundations.

Permits and land rights

Challenge

Land use, environmental and social impact assessments and grid permits must be in place before construction.

Our approach

Support with permit documentation and early involvement of landowners and local communities.

What you receive with our offer

Before you commit, you know exactly what the plant will produce and what it will cost.

  • Energy yield forecast based on local irradiation data
  • CO₂ savings over the full plant lifetime
  • Complete bill of quantities down to the last metre of cable
  • Fixed price, held for the entire offer period
  • Module and inverter prices secured through our long-term supply agreements
  • Construction schedule up to grid connection

Frequently asked questions

How large are the solar parks you build?

We build utility-scale plants in the megawatt range, including transformer stations, medium-voltage collection grids and the connection to the transmission grid via a substation.

Which foundation is used for a solar park?

It depends on the soil. Rammed steel posts are the standard on load-bearing soils, ground screws are used on stony ground, and concrete foundations on rock or shifting desert sand. Pull-out tests on site decide.

How long does it take to build a solar park?

Because planning, procurement and construction are in one hand, plants move from contract to operation in a short time. The exact schedule depends on size, permits, logistics and grid connection and is part of every offer.

How do you deal with dust and heat?

We select modules with a low temperature coefficient, ventilate inverter stations, size cables for local ambient temperatures and plan tilt, row spacing and access routes for a water-saving cleaning concept.

Planning a solar park?

Send us the site location and area. We will come back with a first assessment.

Send an enquiry